The Four Changes: Standard, Normal, Expedited, and Emergency
Table of Contents |
---|
|
The 4 Types of Changes
When you select 'Create New' under the change field, you are met with four change options:
- Standard: Select from available pre-approved change templates. These changes do not require additional authorization once the standard change template has been approved.
- Normal Change : Normal Change implemented after required lead time (>= 5 business days). Authorization required varies depending on risk.
- Expedited: Normal Change requiring implementation ahead of required lead time (> 48 hours and < 5 business days). Authorization required varies depending on risk.
- Emergency: Normal Change requiring implementation a.s.a.p (<= 48 hours) and intended to resolve or avert and outage or degradation. Authorization required follows the ITS Incident Management Process.
NOTE: It is important you understand the Change Request Lifecycle which you can view at KB0018317.
For more information on which change should be used when, please view:
Standard Change
The most common type of change is a Standard Change. Standard changes make use of a pre-authorized Standard Change Template which is submitted by the requester to the change approver for review and scheduling.
Standard Change - A change that is pre-authorized and is created from an active Standard Change Template and has the following attributes:
- Low risk/regularly occurring
- Well- documented with specific procedural instructions
- Clearly defined roles and responsibilities
- Known duration
- High success rate
Standard Change Template - A pre-populated Request fro Change (RFC) that, when active, is used to create Standard RFCs. Must be completed for every Standard Change.
Change Approver - Typically fulfilled by the Service Owner and responsible for review, scheduling (publishing to Maintenance Window on the Change Calendar), and authorization of RFC's.
Next, the Change Implementer (often, the same person as the Change Requester) executes the change and verifies the result. if the change is successful, the Change Requester closes out the RFC.
If the change failed, a Post Implementation Review (PIR) meeting and a report is required. Failed Standard Changes additionally require a review of the Standard Change Template.
Normal Change
A Normal Change has the following unique attributes:
- Does not have the same low risk or repeatable quality of a Standard Change
- Has a nonzero impact to customers of the IT service
- Does not need to be implemented immediately as with Emergency changes or within 48hrs as with an Expedited change
- Normal changes pass through all stages of the Change Lifecycle.
- This is the only change type to pass through the Assess lifecycle stage, requiring action by the Change Reviewer.
Change Reviewer - Validates that the change is justified, technically ready, and has a sound Risk Assessment Value (RAV) with appropriate mitigations in place.
Expedited Change
Requires accelerated authorization but does not meet the requirements for an immediate Emergency Change. Think, "accelerated Normal change".
An Expedited Change has the following unique attributes:
- Normal Change requires implementation ahead of the communication lead time
- Implementation does not need to occur within forty-eight (48) hours.
Emergency Change
An emergency Request for Change (RFC) will be submitted after implementing a change to resolve an outage or prevent an imminent outage.
An Emergency Change has the following unique attributes:
- Resolves or prevents an imminent outage, system degradation, or service failure.
- Implementation must occur within forty-eight (48) hours
- Emergency RFCs move from Create directly to Review and may not be cancelled because the change has already been implemented as part of resolving the incident.